Section 10255.  


Latest version.
  • Upon such termination, the director may take possession of and use all or any part of the contractor's materials, tools, equipment, and appliances upon the premises to complete the contract. Thereupon, he may permit the surety to complete or cause the contract work to be completed, or he may direct that all or any part of the work be completed by day's labor or by employment of other contractors on informal contracts, or both.

(Enacted by Stats. 1981, Ch. 306.)