Section 44283.  


Latest version.
  • (a) Grants shall not be made for projects with a cost-effectiveness, calculated in accordance with this section, of more than thirteen thousand six hundred dollars ($13,600) per ton of NOx reduced in California or a higher value that reflects state consumer price index adjustments on or after January 1, 2006, as determined by the state board. For projects obtaining reactive organic gas and particulate matter reductions, the state board shall determine appropriate adjustment factors to calculate a weighted cost-effectiveness.

    (b) Only covered emission reductions occurring in this state shall be included in the cost-effectiveness determination. The extent to which emissions generated at sea contribute to air quality in California nonattainment areas shall be incorporated into these methodologies based on a reasonable assessment of currently available information and modeling assumptions.

    (c) The state board shall develop protocols for calculating the surplus covered emission reductions in California from representative project types over the life of the project.

    (d) The cost of the covered emission reduction is the amount of the grant from the program, including matching funds provided pursuant to subdivision (e) of Section 44287, plus any other state funds, or funds under the district's budget authority or fiduciary control, provided toward the project, not including funds described in paragraphs (1) and (2) of subdivision (a) of Section 44287.2. The state board shall establish reasonable methodologies for evaluating project cost-effectiveness, consistent with the definition contained in paragraph (4) of subdivision (a) of Section 44275, and with accepted methods, taking into account a fair and reasonable discount rate or time value of public funds.

    (e) A grant shall not be made that, net of taxes, provides the applicant with funds in excess of the incremental cost of the project. Incremental lease costs may be capitalized according to guidelines adopted by the state board so that these incremental costs may be offset by a one-time grant award.

    (f) Funds under a district's budget authority or fiduciary control may be used to pay for the incremental cost of liquid or gaseous fuel, other than standard gasoline or diesel, which is integral to a covered emission reducing technology that is part of a project receiving grant funding under the program. The fuel shall be approved for sale by the state board. The incremental fuel cost over the expected lifetime of the vehicle may be offset by the district if the project as a whole, including the incremental fuel cost, meets all of the requirements of this chapter, including the maximum allowed cost-effectiveness. The state board shall develop an appropriate methodology for converting incremental fuel costs over the vehicle lifetime into an initial cost for the purposes of determining project cost-effectiveness. Incremental fuel costs shall not be included in project costs for fuels dispensed from any facility that was funded, in whole or in part, from the fund.

    (g) For purposes of determining any grant amount pursuant to this chapter, the incremental cost of any new purchase, retrofit, repower, or add-on equipment shall be reduced by the value of any current financial incentive that directly reduces the project price, including any tax credits or deductions, grants, or other public financial assistance, not including funds described in paragraphs (1) and (2) of subdivision (a) of Section 44287.2. Project proponents applying for funding shall be required to state in their application any other public financial assistance to the project.

    (h) For projects that would repower off-road equipment by replacing uncontrolled diesel engines with new, certified diesel engines, the state board may establish maximum grant award amounts per repower. A repower project shall also be subject to the incremental cost maximum pursuant to subdivision (e).

    (i) After study of available emission reduction technologies and costs and after public notice and comment, the state board may reduce the values of the maximum grant award criteria stated in this section to improve the ability of the program to achieve its goals. Every year the state board shall adjust the maximum cost-effectiveness amount established in subdivision (a) and any per-project maximum set by the state board pursuant to subdivision (h) to account for inflation.

    (j) This section shall remain in effect only until January 1, 2024, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2024, deletes or extends that date.

(Amended (as amended by Stats. 2010, Ch. 571, Sec. 1) by Stats. 2013, Ch. 401, Sec. 23. Effective September 28, 2013. Repealed as of January 1, 2024, by its own provisions. See later operative version, as amended by Sec. 24 of Ch. 401.)