Section 8670.31.  


Latest version.
  • (a) Each oil spill contingency plan required under this article shall be submitted to the administrator before a tank vessel, nontank vessel, or vessel carrying oil as secondary cargo operates in the marine waters of the state, or before a marine facility, small marine fueling facility, or mobile transfer unit, operates in the marine waters of the state or where an oil spill therefrom could impact marine waters.

    (b) The administrator shall review each submitted contingency plan to determine whether it complies with the administrator's rules, policies, and regulations adopted pursuant to Section 8670.28 and 8670.29.

    (c) Each contingency plan submitted shall be approved or disapproved within 180 days after receipt by the administrator. The administrator may approve or disapprove portions of a plan. A plan is not deemed approved until all portions are approved pursuant to this section. The disapproved portion shall be subject to the procedures contained in subdivision (d).

    (d) If the administrator finds the submitted contingency plan is inadequate under the rules, policies, and regulations of the administrator, the plan shall be returned to the submitter with written reasons why the plan was found inadequate and, if practicable, suggested modifications or alternatives, if appropriate. The submitter shall submit a new or modified plan within 90 days after the earlier plan was returned, responding to the findings and incorporating any suggested modifications. The resubmittal shall be treated as a new submittal and processed according to the provisions of this section, except that the resubmitted plan shall be deemed approved unless the administrator acts pursuant to subdivision (c). Failure to gain approval after the second submission may be determined by the administrator to be a violation of this chapter.

    (e) The administrator may make inspections and require drills of any oil spill contingency plan that is submitted.

    (f) After the plan has been approved, it shall be resubmitted every five years thereafter. The administrator may require earlier or more frequent resubmission, if warranted. Circumstances that would require an earlier resubmission include, but are not limited to, changes in regulations, new oil spill response technologies, deficiencies identified in the evaluation conducted pursuant to Section 8670.19, or a need for a different oil spill response because of increased need to protect endangered species habitat. The administrator may deny approval of the resubmitted plan if it is no longer considered adequate according to the adopted rules, regulations, and policies of the administrator at the time of resubmission.

    (g) (1) Each operator of a tank vessel, vessel carrying oil as a secondary cargo, or marine facility who is required to file an oil spill response plan or update pursuant to provisions of federal law regulating marine oil spill response plans shall, for informational purposes only, submit a copy of that plan or update to the administrator at the time that it is approved by the relevant federal agency.

    (2) A tank vessel, vessel carrying oil as a secondary cargo, or marine facility operator is not required to submit a copy of the response plan or update specified in paragraph (1) to the administrator if either the vessel or facility is exempt from having to file a response plan with the state, or if the content of the plan submitted by the operator pursuant to Section 8670.29 is substantially the same as the federal response plan or update.

(Amended by Stats. 2004, Ch. 796, Sec. 26. Effective January 1, 2005.)