California Law (Last Updated: March 4, 2014) |
Education Code - EDC |
Title 3. POSTSECONDARY EDUCATION |
Division 7. COMMUNITY COLLEGES |
Part 49. COMMUNITY COLLEGES, EDUCATION FACILITIES |
Chapter 3.5. Design-Build Contracts |
Section 81704.
-
(a) Any design-build entity that is selected to design and build a project pursuant to this chapter shall possess or obtain sufficient bonding to cover the contract amount for nondesign services, and errors and omission insurance coverage sufficient to cover all design and architectural services provided in the contract. This chapter does not prohibit a general or engineering contractor from being designated the lead entity on a design-build entity for the purposes of purchasing necessary bonding to cover the activities of the design-build entity.
(b) Any payment or performance bond written for the purposes of this chapter shall use a bond form developed by the Department of General Services pursuant to subdivision (i) of Section 14661 of the Government Code. The purpose of this subdivision is to promote uniformity of bond forms to be used on community college district design-build projects throughout the state.
(c) (1) All subcontracts that were not listed by the design-build entity in accordance with Section 81703 shall be awarded by the design-build entity in accordance with the design-build process set forth by the community college district in the design-build package.
(2) The design-build entity shall do all of the following:
(A) Provide public notice of the availability of work to be subcontracted.
(B) Provide a fixed date and time on which the subcontracted work will be awarded.
(3) Subcontractors bidding on contracts pursuant to this subdivision shall be afforded the protections contained in Chapter 4 (commencing with Section 4100) of Part 1 of Division 2 of the Public Contract Code.
(4) (A) If the community college district elects to award a project pursuant to this section, retention proceeds withheld by the community college district from the design-build entity shall not exceed 5 percent if a performance and payment bond, issued by an admitted surety insurer, is required in the solicitation of bids.
(B) In a contract between the design-build entity and a subcontractor, and in a contract between a subcontractor and any subcontractor thereunder, the percentage of the retention proceeds withheld shall not exceed the percentage specified in the contract between the community college district and the design-build entity. If the design-build entity provides written notice to any subcontractor who is not a member of the design-build entity, prior to or at the time the bid is requested, that a bond may be required and the subcontractor subsequently is unable or refuses to furnish a bond to the design-build entity, then the design-build entity may withhold retention proceeds in excess of the percentage specified in the contract between the community college district and the design-build entity from any payment made by the design-build entity to the subcontractor.
(5) In accordance with the provisions of applicable state law, the design-build entity may be permitted to substitute securities in lieu of the withholding from progress payments. Substitutions shall be made in accordance with Section 22300 of the Public Contract Code.
(d) (1) For contracts for public works projects awarded prior to the effective date of the regulations adopted by the Department of Industrial Relations pursuant to subdivision (g) of Section 1771.5 of the Labor Code, the community college district shall establish and enforce a labor compliance program containing the requirements outlined in Section 1771.5 of the Labor Code or shall contract with a third party to operate a labor compliance program containing the requirements outlined in Section 1771.5 of the Labor Code. This requirement shall not apply to projects where the community college district or the design-build entity has entered into a collective bargaining agreement that binds all of the contractors performing work on the project.
(2) For contracts for public works projects awarded on or after the effective date of the regulations adopted by the Department of Industrial Relations pursuant to subdivision (g) of Section 1771.5 of the Labor Code, the community college district shall reimburse the department for its reasonable and directly related costs of performing prevailing wage monitoring and enforcement on public works projects, pursuant to rates established by the department as set forth in subdivision (h) of Section 1771.5 of the Labor Code. All moneys collected pursuant to this subdivision shall be deposited in the State Public Works Enforcement Fund created by Section 1771.3 of the Labor Code, and shall be used only for enforcement of prevailing wage requirements on those projects.
(3) In lieu of reimbursing the Department of Industrial Relations for its reasonable and directly related costs of performing monitoring and enforcement on public works projects, the community college district may elect to continue operating an existing previously approved labor compliance program to monitor and enforce prevailing wage requirements on the project if it has either not contracted with a third party to conduct its labor compliance program and requests and receives approval from the department to continue its existing program or it enters into a collective bargaining agreement that binds all of the contractors performing work on the project and that includes a mechanism for resolving disputes about the payment of wages.