Section 9362.  


Latest version.
  • (a) Not later than 10 days after each of the following events, the public entity shall give notice to a claimant that has given a stop payment notice of the time within which an action to enforce payment of the claim stated in the stop payment notice must be commenced:

    (1) Completion of a public works contract, whether by acceptance or cessation.

    (2) Recordation of a notice of cessation or completion.

    (b) The notice shall comply with the requirements of Chapter 2 (commencing with Section 8100) of Title 1.

    (c) A public entity need not give notice under this section unless the claimant has paid the public entity ten dollars ($10) at the time of giving the stop payment notice.

(Added by Stats. 2010, Ch. 697, Sec. 20. Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697.)