California Law (Last Updated: March 4, 2014) |
Civil Code - CIV |
Division 4. GENERAL PROVISIONS |
Part 6. WORKS OF IMPROVEMENT |
Title 2. PRIVATE WORKS OF IMPROVEMENT |
Chapter 8. Prompt Payment |
ARTICLE 2. Retention Payment |
Section 8814.
-
(a) If a direct contractor has withheld a retention from one or more subcontractors, the direct contractor shall, within 10 days after receiving all or part of a retention payment, pay to each subcontractor from whom retention has been withheld that subcontractor's share of the payment.
(b) If a retention received by the direct contractor is specifically designated for a particular subcontractor, the direct contractor shall pay the retention payment to the designated subcontractor, if consistent with the terms of the subcontract.
(c) If a good faith dispute exists between the direct contractor and a subcontractor, the direct contractor may withhold from the retention to the subcontractor an amount not in excess of 150 percent of the estimated value of the disputed amount.