California Law (Last Updated: March 4, 2014) |
Civil Code - CIV |
Division 4. GENERAL PROVISIONS |
Part 6. WORKS OF IMPROVEMENT |
Title 2. PRIVATE WORKS OF IMPROVEMENT |
Chapter 4. Mechanics Lien |
ARTICLE 3. Amount of Lien |
Section 8432.
Latest version.
-
(a) A lien does not extend to work, whether or not the work is authorized by a direct contractor or subcontractor, if the work is not included in a direct contract or a modification of that contract, and the claimant had actual knowledge or constructive notice of the provisions of that contract or modification before providing the work.
(b) The filing of a contract or modification of that contract with the county recorder, before the commencement of a work of improvement, is constructive notice of the provisions of the contract or modification to a person providing work on that work of improvement.
(Added by Stats. 2010, Ch. 697, Sec. 20. Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697.)