Section 8414.  


Latest version.
  • A claimant other than a direct contractor may not enforce a lien unless the claimant records a claim of lien within the following times:

    (a) After the claimant ceases to provide work.

    (b) Before the earlier of the following times:

    (1) Ninety days after completion of the work of improvement.

    (2) Thirty days after the owner records a notice of completion or cessation.

(Added by Stats. 2010, Ch. 697, Sec. 20. Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697.)