Section 8186.  


Latest version.
  • If a work of improvement is made pursuant to two or more direct contracts, each covering a portion of the work of improvement:

    (a) The owner may record a notice of completion of a direct contract for a portion of the work of improvement. On recordation of the notice of completion, for the purpose of Sections 8412 and 8414, a direct contractor is deemed to have completed the contract for which the notice of completion is recorded and a claimant other than a direct contractor is deemed to have ceased providing work.

    (b) If the owner does not record a notice of completion under this section, the period for recording a claim of lien is that provided in Sections 8412 and 8414.

(Added by Stats. 2010, Ch. 697, Sec. 20. Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697.)